Pushing back the IcedTea6 1.11 release: 2012-01-25

Andrew Hughes ahughes at redhat.com
Mon Jan 23 13:21:03 PST 2012


----- Original Message -----
> On 01/18/2012 11:23 AM, Omair Majid wrote:
> > How does 1 week (2012-01-25) sound?
> >
> 
> Things are looking much better with the arm stuff now. It looks like
> IcedTea6 1.11 on 2012-01-25 will be doable.
> 

I don't think this is a good idea.  There's an upcoming security release
that will make such a release obsolete just three weeks after:

http://www.oracle.com/technetwork/topics/security/alerts-086861.html

Would it not be better to just wait and release 1.11 with these security
fixes?  I also still see a large number of ARM patches coming in from
Andrew which suggests the branch isn't as stable as you say.  It especially
worries me that this last hsdis patch was pushed to the release branch
when it was still under discussion.

I don't see any benefit in rushing this release.  Let's take time and make
a worthwhile release.

> Cheers,
> Omair
> 

-- 
Andrew :)

Free Java Software Engineer
Red Hat, Inc. (http://www.redhat.com)

PGP Key: 248BDC07 (https://keys.indymedia.org/)
Fingerprint = EC5A 1F5E C0AD 1D15 8F1F  8F91 3B96 A578 248B DC07




More information about the distro-pkg-dev mailing list