JDK 13 is now in Rampdown Phase One

mark.reinhold at oracle.com mark.reinhold at oracle.com
Thu Jun 13 20:33:58 UTC 2019


Per the JDK 13 schedule [1], we are now in Rampdown Phase One.

The overall feature set is frozen.  No further JEPs will be targeted to
this release.

We’ve forked the main-line source repository, jdk/jdk, to the jdk/jdk13
stabilization repository.  Any changes pushed to jdk/jdk are now bound
for JDK 14, as noted previously [2].

The stabilization repository is open for select bug fixes and, with
approval, late enhancements per JEP 3, the JDK Release Process [3].
If you’re responsible for any of the bugs on the RDP 1 candidate-bug
list [3] then please see JEP 3 for guidance on how to handle them.

- Mark


[1] http://openjdk.java.net/projects/jdk/13/#Schedule
[2] https://mail.openjdk.java.net/pipermail/jdk-dev/2019-June/003051.html
[3] http://openjdk.java.net/jeps/3
[4] http://j.mp/jdk-rdp-1