Reminder: file JDK 21 CSRs well ahead of June 8, 2023 rampdown 1 start
Joseph D. Darcy
joe.darcy at oracle.com
Wed Apr 12 18:05:54 UTC 2023
Hello,
Per the JDK 21 schedule (https://openjdk.org/projects/jdk/21/), the
rampdown 1 of JDK 23 starts on June 8, 2023, about eight weeks from today.
An advanced reminder to factor in sufficient review time for any
projects needing CSR review before getting pushed into JDK 21, which
includes JEPs. Large projects, including JEPs, should often use the
two-phase CSR process (https://wiki.openjdk.java.net/display/csr/Main)
rather than the one-phase process. The nominal SLA for each CSR phase is
one week. To accommodate the possibility of needing to respond to
feedback from the CSR, I recommend a large project that has not already
had CSR review budget at least four weeks of CSR review time ahead of a
planned integration date.
Particularly large or complex projects should factor in additional time.
A JEP should have gone through the first phase of CSR review, getting to
Provisional state, before being Proposed to Target for a release. Please
plan accordingly.
Cheers,
-Joe