Reminder: file JDK 23 CSRs well ahead of June 6, 2024 rampdown 1 start
Joe Darcy
joe.darcy at oracle.com
Thu May 16 16:13:40 UTC 2024
Thanks for the CSRs submitted in the interim; now just three weeks until
JDK 23 rampdown 1,
-Joe
On 5/1/2024 10:04 AM, Joseph D. Darcy wrote:
> Hello,
>
> Per the JDK 23 schedule (https://openjdk.org/projects/jdk/23/), the
> rampdown 1 of JDK 23 starts on June 6, 2026, just over five weeks from
> today.
>
> An advanced reminder to factor in sufficient review time for any
> projects needing CSR review before getting pushed into JDK 23, which
> includes JEPs. Large projects, including JEPs, should often use the
> two-phase CSR process (https://wiki.openjdk.java.net/display/csr/Main)
> rather than the one-phase process. The nominal SLA for each CSR phase
> is one week. To accommodate the possibility of needing to respond to
> feedback from the CSR, I recommend a large project that has not
> already had CSR review budget at least four weeks of CSR review time
> ahead of a planned integration date.
>
> Particularly large or complex projects should factor in additional time.
>
> A JEP should have gone through the first phase of CSR review, getting
> to Provisional state, before being Proposed to Target for a release.
> Please plan accordingly.
>
> Cheers,
>
> -Joe
> CSR Lead
>