How long is the jdk12u repo still open for fixes for 12.0.2?
rob.mckenna at oracle.com
rob.mckenna at oracle.com
Fri May 10 14:26:08 UTC 2019
Hi Christoph,
Given the short lifecycle of 12, we're doing our best to get as many of
the requests in as possible. As such jdk12u-fix-requests are treated as
critical requests. Any fix that won't be accepted for 12.0.2 will not be
approved until the fixVersion on the repo changes.
There is no hard and fast cutoff date for these requests, but I would
expect to stop accepting them within the next couple of weeks. (at that
point I'll change the hgupdater version on jdk12u.
-Rob
On 10/05/19 09:40, Langer, Christoph wrote:
> Hi jdk12u maintainers,
>
> I can see that still fix requests for jdk12u are approved and when pushed, they target to 12.0.2. My question: How long will jdk12u still collect fixes for 12.0.2?
>
> In the Wiki [0] I can read that RDP2 is late April which has already passed. And I assumed that that's the cutoff date after which pushes to jdk12u won't go directly into 12.0.2 any longer?
>
> Thanks
> Christoph
>
> [0] https://wiki.openjdk.java.net/display/JDKUpdates/JDK12u
>
>
>
More information about the jdk-updates-dev
mailing list