Build and Integration schedule -- skip weeks
Mark Reinhold
mr at sun.com
Fri May 8 09:01:29 PDT 2009
> Date: Fri, 08 May 2009 08:20:13 -0700
> From: xiomara.jayasena at sun.com
> I was under the impression that b60 was going to be the last build for
> M3 and according to the Calendar here:
> http://openjdk.java.net/projects/jdk7/calendar/
> it shows that b60 is the last build for M3. Are we saying that b59 is
> now going to be the last build in M3 then?
Build 60 is the last scheduled build for M3. It's the showstopper build.
If we need it, we'll do it; if we don't, then we'll skip it. I suggest
you leave 60 in the schedule until we make that decision.
If we skip 60 then that does raise the question of whether what's now
called 61 should be renamed to 60, and so forth for all following builds.
Personally I'd prefer to keep the present numbering and just document the
fact that we skipped 60. I tend to view build numbers as part of the
calendar. If you don't do something on a particular day then that
doesn't mean you remove the day from the calendar, it just means that
you do it on some later day.
What do others think?
- Mark
More information about the jdk7-rt
mailing list