On 06/02/2013 23:33, David Holmes wrote:
>
> As I recall those post modularization steps were about to be thrown 
> out for a completely new process that did the compilation and 
> modularization up front. The patches for the great src reorganization 
> had been sent out but I don't think they were committed ?
For the source code re-organization then the shuffle/unshuffle scripts 
are in the top-level repo (in make/scripts/shuffle). It remains to me 
seen when the right time will be to actually do the reorganization. I 
think we need to get more experience with it first.

On regards the build then clearly we are living on borrowed time. For 
the short term we would like move the post-processing to the new build. 
More medium term we need to continue the work that Erik started last 
year so that we compile the JDK as modules.