Reminder: file JDK 25 CSRs well ahead of rampdown 1 start

Joseph D. Darcy joe.darcy at oracle.com
Thu Apr 3 19:26:56 UTC 2025


Hello,

Per the proposed JDK 25 schedule 
(https://mail.openjdk.org/pipermail/jdk-dev/2025-April/009870.html), the 
rampdown 1 of JDK 25 would start on June 5, 2025, nine weeks from today.

An advanced reminder to factor in sufficient review time for any 
projects needing CSR review before getting pushed into JDK 25, which 
includes JEPs. Large projects, including JEPs, should often use the 
two-phase CSR process (https://wiki.openjdk.java.net/display/csr/Main) 
rather than the one-phase process. The nominal SLA for each CSR phase is 
one week. To accommodate the possibility of needing to respond to 
feedback from the CSR, I recommend a large project that has not already 
had CSR review budget at least four weeks of CSR review time ahead of an 
anticipated integration date.

Particularly large or complex projects should factor in additional time.

A JEP should have gone through the first phase of CSR review, getting to 
Provisional state, before being Proposed to Target for a release. Please 
plan accordingly.

Cheers,

-Joe